(KZN.RU,
October 13, Alsu Safina). The first stage of roadworks will be completed by
early November in Kazan, as a result of which the road section on Barudi Str.
will be expanded to four lanes (from Batyrshin Str.to Serov Str.) and there
will be turnarounds on Serov Str. Ilsur Metshin, the Mayor of Kazan, inspected
the progress of the work.
Roadworks
began on this site in August and are conducted on an area of about 8 thousand
square meters. The asphalt will be replaced at 2.5 thousand square meters, and
work on the expansion of the carriageway and the settling of turnarounds will
be carried out on an area of 5.5 thousand square meters. The cost of the
facility is 49.5 million rubles. This year only the lower layer of asphalt will
be laid, the object will be ready completely in the next repair season.
During the
meeting, Eduard Danilov, the director of the GKU “Glavtatdortrans”, who acts as
the customer, and Airat Minnullin, the general director of the contract
organization OOO “Volgadorstroy”, reported to the Mayor about the progress of
the work. There is a marshy ground in this area, which required additional
drainage and tie-in to the storm collector. In addition, engineering
communications were transferred. For today, the foundation for the construction
of the road has been completely excavated in Barudi Street, where the road is
being expanded, the underlying layer of sand and the base of crushed stone are
laid, and the side walls are installed. Today the installation of the upper
layer of the black rubble base begins. This is necessary to enhance the bearing
capacity and extend the life of the road. After that, the laying of the bottom
layer of asphalt begins within a week.
“In
October, we plan to finish the asphalt-concrete coating in the lower layer and
leave the top layer for the spring”, said Eduard Danilov and explained that
this will ensure the quality of the road. The movement on this site and on
turnarounds at the intersection of Barudi, Voskhod, and Serov streets will be
launched this year. In addition, road signs will be installed and 9 traffic
lights will be put into operation. Also, new fences will be installed on the streets
of Barudi, Serov, and Voskhod.
This
section of the road is one of the most problematic in the district and local
residents have repeatedly complained about it. Since the beginning of this
year, 13 road accidents on Serov Street and 25 at the intersection of Serov and
Barudi streets have been registered. The Mayor of the city drew attention to
the intensity of the traffic there.
The
construction of new residential buildings is being carried out in the
micro-district, which will soon affect the population increase by 3 thousand
people.
The
expansion of the road and the arrangement turnarounds will allow dividing
traffic flows, unloading the intersection of Serov and Barudi streets and
improving transport safety.
“This small
solution will unload the whole transport node”, noted the head of the city.
Ilsur Metshin also marked that it is necessary to carry out the work within the
deadlines.
Sergey
Mironov, the head of the Kirovsky and Moskovsky districts’ administration,
Albert Ibragimov, the first deputy chairman of the Committee for External
Improvement, and others also took part in the meeting.
This year
about 3 million square meters of roads and yards will be repaired in Kazan.