(KZN.RU, September 20, Alsu Safina). Ilsur Metshin, the Mayor of Kazan, inspected the construction of the metro station “Dubravnaya” at the intersection of Zorge and Fuchik streets. Actual issues related to the commissioning of the facility were discussed during the on-site meeting. According to Marat Rakhimov, the general director of the AO “Kazmetrostroy”, the completion of all works is planned by the end of the year.
M. Rakhimov said that the work was completed on the construction of monolithic station structures in the amount of 27 thousand 209 cubic meters of concrete (vestibules №1, 2, platform area, ventilation unit, etc.). Now the finishing and installation works are in full swing at the metro station “Dubravnaya”. “After that, it is necessary to starting-up and adjustment the equipment, providing constant power supply, so that everything can be tested in the operating mode”, he said.
Ilsur Metshin, accompanied by Marat Rakhimov, Asfan Galyavov, the general director of the MUE “Metroelectrotrans”, and Andrey Lobov, the head of the Vakhitovsky and Privolzhsky districts’ administration, went down into one of the station's vestibules and the platform where the finishing works are underway. Workers are cladding the walls and floors of the station, in addition, they are installing heating, ventilation, and sewerage. The AO “Kazmetrostroy” and the OOO “PSO “Kazan” carry out works on the site. Part of the work related to video surveillance systems, access control, payment of travel, fire alarm, and a number of others, at the facility are carried out by the MUE “Metroelectrotrans”. In addition, the company will improve the territory above the metro station “Dubravnaya” after the completion of underground work.
During the meeting, the Mayor of Kazan asked Asfan Galyavov how the passenger traffic will change after the new station is delivered. The head of “Metroelectrotrans” noted that the redistribution of passenger traffic will take place between the stations “Prospekt Pobedy” and “Dubravnaya”. It is assumed that 3-5 thousand people per day will pass through the new station. For today, the passenger traffic of the underground is about 100 thousand people per day.
Also, the Mayor inspected the office premises, stairways (5 entrances are planned at the station), lift shafts, which are equipped for low-mobility groups of the population. The work is underway to build monolithic structures for a prospective transition to the second line, the remaining staircase station gatherings, and a prospective exit to the second line (the volume of monolithic reinforced concrete structures is 723 cubic meters of concrete).
The construction of the final station of the first underground line “Dubravnaya” has been carried out since 2014. On March 20, 2015, the drifting of the right distillation tunnel “Dubravnaya” – “Prospekt Pobedy” was started, which was successfully completed in the summer. On December 23, 2015, the TPK “Lovat” started the tunneling of the left distillation tunnel and completed it in April 2016.