(KZN.RU August 16, Zilya Gayfi). Four houses on 352
apartments on M. Gafuri Str., erecting within the program of construction of
residential houses for the resettlement of citizens from damaged houses in
2016, prepared to be passed in Kazan. Decoration works are completed and the
improvement of the local area is performed on the objects. Ilsur Metshin, the Mayor
of Kazan, estimated the readiness of facilities for commissioning and
subsequent resettlement today.
Alexey Pesoshin, the first deputy Prime Minister of
Tatarstan, Irek Faizullin, the minister of Construction, architecture and utilities
of RT, Talgat Abdullin, the executive director of the State Housing Fund under
the President of RT, Denis Kalinkin, the head of the Executive Committee, Azat
Nigmatzyanov, the first deputy head of the Executive Committee on urban policy,
Marcel Abdulhakov, the head of Housing policy, Andrei Lobov, the head of Vakhitovskiy
and Privolzhskiy districts administration, and representatives of design and
contracting companies took part in the meeting.
The construction of four residential buildings with
352 apartments (house №1, 2, 4, 5 and 88 apartments and non-residential premises)
on the street M. Gafuri in the Vakhitovskiy district began in August 2015. State
housing fund under the President of RT became the investor of the project, the
Overhaul Office of the Executive Committee is the technical customer, the
company Tatinvestgrazhdanproekt, OOO “Ak-Tash”, and OAO “Kazantsentrstroy” were
chosen as the designer and general contractor.
Ilsur Metshin inspected the local area of houses №4
and 5, where a children's playground is landscaped, asphalt surface is laid and
construction of container yard is carried out. “Houses №4 and 5 are almost
ready, practically everything may be passed to the State Construction
Supervision, if the water supply will be ensured and the issue with
communication will be resolved, then within a week it will be possible to pass
these two houses. Readiness of houses №1 and 2 is estimated to be less;
however, they also can be passed in a month after solving the problem with
communications. Thus, the questions of the water supply, sewage system and a
storm water drain are the main now”, reported Azat Nigmatzyanov about the degree
of objects readiness.
Builders have begun to remove the top layer of asphalt
and tram tracks for laying of water pipeline on the road of the M. Gafuri street
today. All work on the site should be completed by September 1, since one of
the school bus routes lies on the street.
Ilsur Metshin noted that the program of resettlement
of residents from damaged houses is a priority for the city program, which is
waited by thousands of Kazan citizens, so it is important to comply with the
previously announced terms.
It is planned to populate four houses on the M. Gafuri
street before the end of the year. Apartments in them (one-roomed, two-roomed
and three-roomed) will be sold with the final decoration. Talgat Abdullin said
earlier that additional resettlement options will be offered to residents of
damaged houses, including apartments in a newly built residential complex “Salavat
Cupere”.
151 residential building was recognized as damaged in
Kazan in January 1, 2012. For today, the program includes 96 houses on 1674
apartments with a total area of 53,500.10 square meters, which are home to
nearly 5,000 residents. All these houses are planned to resettle to the end of
2017.