(KZN.RU,
July 2, Ksenia Shvetsova). 45 kilometers of networks have been constructed and
reconstructed, 3 pump stations have been put into operation, and new wells have
been drilled in order to normalize the water supply in Kazan settlements.
However, this is not enough to improve the quality of water supply in all urban
housing estates. A federal program is needed to solve this problem. Ilsur
Metshin, the Mayor of Kazan, expressed such an opinion today at the Business
Monday.
Andrey
Egorov, the general director of MUP “Vodokanal”, said there are already first
significant results in improving the quality of water supply. For today, the
reconstruction of the North-Eastern water supply unit has been carried out, 3
pump stations have been built and put into operation. In addition, 12 wells
have been repaired and drilled in settlements Mirny and Sukhaya Reka.
About 45
kilometers of networks have been built and repaired in the settlement
Konstantinovka, Samosyrovo, Nagorny, Severny, Karier, Salmachi, Borisoglebsk,
Petrovsky, and others. “The length of the constructed networks is commensurable
with the bypass road Mamadyshsky Tract – Zalesny”, explained A. Egorov. He
added that with the support of the President of the RT, a water purification
station was built in Kulseitovo settlement, new networks have been built in the
settlement of the Officers, Koyashli, and Aki. Their total length was 20 km,
and the sum of all capital investments for 6 years was more than 600 million
rubles.
Despite a
large amount of work done, there are a number of settlement streets where water
supplies are interrupted, noted the reporter. “This is due to the fact that the
networks in the settlements were built spontaneously, for decades by the
residents themselves with violation of all norms”, believes A. Egorov. More
than 95% of networks are accepted to be reorganized. However, all of them
require a large-scale reconstruction.
According
to A. Egorov, for today a preliminary pre-project plan for water supply
normalization has been drawn up. The construction sites for two new village
pumping stations, 70 km of main and street networks, as well as the
reconstruction of 130 km of existing networks and four facilities have been
identified based on the calculations.
“The amount
of capital repairs of all city water supply networks in the water supply tariff
is set at 112 million rubles in 2018. It is less than 5 percent of the total
annual demand”, noted the reporter. “We are working on the repositioning of
narrow places and adjusting the water supply modes. We are attracting
water-carrier equipment in the most critical places. But additional funding and
participation in federal and regional programs are required for a systemic
solution of the issue”, noted A. Egorov.
Ilsur
Metshin also noted that, given the growth rate of the number of urban
settlements, despite the large amount of ongoing work it would be impossible to
ensure quality water supply without the involvement of additional resources.
“There is
no investment surcharge in the tariff for 6 years, just as there is no ready
solution to the problem. But we will find a solution to this problem with
colleagues from the Ministry of Housing and Communal Services, the Government
of the Republic, with the support of our President. We will seek internal
resources, prepare documents and apply to the federal center”, said I. Metshin.