(KZN.RU,
September 26, Alsu Safina). Ilsur Metshin, the Mayor of Kazan, congratulated
the shareholders of the fourth section on 136 apartments on Urmanche Street in
the RC “Solnechny Gorod” with the long-awaited housing. Now the work on the
pedestrian overpass is carrying out near the house. In November, residents of
the neighborhood will be able to cross the road safely. It is planned to extend
the tram tracks and organize a few more stops on the route №5 for the
convenience of residents next summer.
GC “FON”
began to build this residential complex but the construction was stopped. The
municipality was involved in solving the problem.
“Together,
we did it, 136 apartments were put into operation”, said the Mayor. “Now you
will have an opportunity to live here a happy life”. “We try to implement what
we promised and planned”, he added. The company “Dorstroy Packaging” of R.
Ramazanov, the deputy of the Kazan City Duma, invested in the completion of the
house. This became possible due to the Decree of the President of the RT
UP-1004 of 11.14.2016, which allows giving land for housing construction
without trades to investors participating in solving the problems of shared
construction.
Shareholders
thanked the Mayor of Kazan and Azat Nigmatzyanov, the first deputy head of the
Executive Committee, for the help and support provided in solving the complex
problem.
Azat
Nigmatzyanov reminded that the President of Tatarstan set the task in the
annual message to the State Council of the RT till the end of the year to
deliver 6 objects of shareholders. “We can say that the first one is done. This
is 136 apartments. We see the happy faces of shareholders. Soon they will be
able to go to the cadastral chamber to register their housing”, said the first
deputy head of the Executive Committee.
The Mayor
of Kazan also informed shareholders that it is planned to complete the
construction of a pedestrian overpass, which adjoins the stylobate, in
November. The residents of the micro-district repeatedly addressed the city
administration with this question. They noted that they had to cross the road
through an unregulated pedestrian crossing, which is not safe. “The track is
becoming lively because of the number of houses. The overpass is necessary for
the safety of people, especially children who go to school and kindergarten”,
marked I. Metshin.
The
pedestrian crossing was laid back in 2008 while building the road along
Urmanche Street. However, the facility and the road were not completed due to
lack of funding. Funds for the completion of the pedestrian crossing were
allocated by Rustam Minnikhanov, the President of Tatarstan.
Now work on
the road infrastructure site continues. Andrey Kulikov, the director of the
contractor organization, the construction company “Ascogroup”, said that
concreting of metal structures is conducted. In addition, the work is underway in
the facility for the installation of staircases, the cleaning of metals with a
sandblasting machine. Once the metal junction structures have been cleaned,
they will be cleaned, painted, and polycarbonate coated.
The
facility will be equipped with two lifts. In general, according to A.Kulikov,
the pedestrian overpass will be provided with everything necessary for the less
mobile groups of the population.
The
elevation of a pedestrian overpass to a meter was necessary to make it possible
to continue the ring tram line. Before the meeting with the shareholders, Ilsur
Metshin, together with Azat Nigmatzyanov and Aidar Abdulkhakov, the chairman of
the Committee on Transport, discussed the development of the tramway ring line.
“We need to
report this issue together with the Minister of Transport and Road Facilities
to the President of the RT. Next summer, it is necessary to extend the tram
line for 2-3 stops and make a turning ring”, said the Mayor. He asked A.
Abdulkhakov how long it will take to design and carry out the work. “The
projectors (“Tatdorproject” – ed.) are involved, the project will be ready by
the next summer”, replied the chairman of the Committee on Transport.
The Mayor
of Kazan told the shareholders about the plans to extend the tram lines. Thanks
to this, residents of the micro-district will a closer stop. “Our further plans
are to ring the “Solnechny Gorod” from Boriskovo, so that tram №5 goes round.
We need serious investments to do this, and the resettlement of suburban areas,
the construction of a junction at the final stop in Boriskovo”, said Ilsur
Metshin.
Andrey
Lobov, the head of the Vakhitovsky and Privolzhsky districts’ administration,
Marat Samigulin, the head of the Department for Capital Construction and
Reconstruction, Diana Akhmetzyanova, director of the OOO “Fon-Riviera”, Sergey
Orlov, the technical director of the GK “Fon”, representatives of contractors
took part in the meeting.