In July, the
second stage of reconstruction of the third northern sewer will begin in Kazan
–on Yamasheva Avenue from Adoratsky Street to Amirkhana Street. Now work is underway
on Chistopolskaya Street, where temporary pipelines have been installed and the
sewer is being flushed. The Mayor of Kazan Ilsur Metshin inspected the progress
of reconstruction.
“Large-scale reconstruction
of the third northern sewer is crucial. Despite the fact that the networks were
laid about 40 years ago, the active use of household chemicals has turned sewer
pipes into a sieve, - the head of the city noted. - To date, builders and
maintenance services have found all the necessary solutions to complete the
reconstruction of the three worn-out sections of the sewer.
The total length
of the sewer, built in 1985 to collect and remove wastewater in Novo-Savinovsky
and Sovetsky districts, including the village of Derbyshki, is 8 km. By
December, it is planned to repair more than 2 km of utilities in disrepair in
three stages.
The sewer section
along Chistopolskaya St., from Meridiannaya St. to Bondarenko St., with a
length of 760 meters, is the most difficult, the Mayor noted, since the work
will be carried out in the middle of a residential area with heavy traffic. To
date, workers have completed the construction of three out of the six wells, as
well as the reconstruction of two existing wells. In addition, six temporary
pipelines with a total length of 1.95 km and six encasement pipes were laid
along Meridiannaya Street for the installation of temporary pumping lines. Now
the workers have started flushing the sewer at 26/5 on Chistopolskaya St.,
First deputy director of the Municipal Unitary Enterprise Vodokanal Marat
Salakhov told the head of the city. About 50 people and 30 special vehicles
work at the facility every day.
Restoration of
the pipeline is carried out by the plastic sleeve method and spiral winding
technology with a lock connection. Marat Salakhov said that in the near future
the workers will start laying the sleeve, which is a special fabric impregnated
with polymer resin. The length of one sleeve is from 50 to 70 m. That is, every
50-70 m, a pit is made, a sleeve is laid under the ground, and then it is
straightened by a stream of water and fills all existing holes.
Next month, the
work will also begin on the site along Yamasheva Ave., from Adoratsky St. to
Amirkhana St., with a length of 850 meters. “Now the design estimate
documentation is undergoing state examination,”- said the first deputy director
of Vodokanal. In addition, documentation is being prepared for work on the
pipeline section along Amirkhana Street, from Chetaeva Street to Chistopolskaya
Street, with a length of 700 meters. “Work on the first two sections is planned
to be completed by September, and on the third – by the end of the year,”- M.
Salakhov reported.
For reference, the
reconstruction of the third northern sewer began in February 2022. Over the
past 10 years, 43 sinkhole collapses have occurred on it, 25 of them in 2021,
all of them have been repaired. The sewer serves more than 850 apartment
buildings with 220 thousand residents, 56 kindergartens, 27 schools, 4
hospitals and 200 administrative buildings.