(KZN.RU,
June 11, Alena Miroshnichenko). The overhaul of kindergarten №235 in Sovetsky
district continues in Kazan. Today, the construction works in a two-story brick
building of 1965, which started in April of this year, have been completed by
30%. They plan to deliver the object by the end of August. Ilsur Metshin, the
Mayor of the Tatarstan’s capital, familiarized himself with the current results
of the overhaul.
Marina
Kolesnikova, the head of the kindergarten, said that since the construction,
the building had only routine repairs for 54 years. Therefore, an integrated
approach to the restoration of the kindergarten building is required. “We are
very grateful that our kindergarten was included in the overhaul program. The
parents are also pleased, they are eagerly awaiting the opening of the
kindergarten”, she said.
“Today we
have completed about 30% of all planned work. We repaired the roof at 90%, we
still have to make the flooring of the painted sheets. This will be done within
a week, now we are waiting for the material delivery”, said Eric Minzaripov,
the head of the subcontracting organization OOO “KultStroy”. The general
contractor is the OOO “RCC Engineering”.
Now
security and fire alarm systems, heating, ventilation and electricity are being
replaced in the building. Within two weeks, the windows will be completely
replaced, and the finishing work will start. In addition, asphalting,
improvement of the territory adjacent to the building, repair of the fence,
installation of tents and small architectural forms are planned at the site.
“From 15 to 20 people work every day at the site. We plan to complete the
repair by August 20”, said E. Minzaripov.
Contractors
and employees of the educational institution work in tandem, noted the manager.
“At the moment, the project of the facade is being discussed. Everyone is
interested in the kindergarten to become beautiful, bright, and meeting all the
requirements of modern education”, marked M. Kolesnikova.
The
kindergarten №235 is designed for 115 children, but 161 children are enrolled
in six groups there. Today, all children are placed in the nearby kindergartens
of the neighborhood.
“Overhaul
of kindergartens is a very important program. We are grateful to Rustam
Minnikhanov, the President of the RT. He decided to hold it, he supports,
finances it, because not a single city, not a single municipality could cope
with it without support”, marked I. Metshin during the inspection. He reminded
that this year the overhaul of 16 kindergartens is scheduled in Kazan. “We have
already repaired the “urgent” buildings that really required quick measures. We
still have 150 out of the 200 kindergartens that require capital repairs. We
have not even passed the equator. There is a lot of work to be done, but we
have finished the most problem points”, the Mayor noted.
After the
inspection, the head of the city promised to assess the work done when the
repair is completed.
Iskander
Giniyatullin, the deputy head of the Executive Committee, Dmitry Anisimov, the
chairman of the Housing and Communal Services Committee, Ilnar Khidiyatov, the
head of the Department of Education, Roman Fathutdinov, the head of the
Sovetsky district’s administration, and others also took part in the
inspection.