(Kazan City
KZN.RU, March 10, Zilya Gayfi). Mayor of Kazan Ilsur Metshin continue detour of
problematic houses built in the city by the equity program. After several
objects of GC "Fon" Mayor visited four unfinished houses of
"Sway", where assessed the extent of the backlog personally and met
with real estate investors. The workshop was attended by the first deputy head
of the Executive Committee on urban policy Azat Nigmatzyanov, Deputy Minister
of Construction, Architecture and Housing and Communal Services of Tatarstan
Vladimir Kudryashov, Chief Engineer of "Sway" Sergey Gordeev, as well
as representatives of RT State Construction and the State Unitary Enterprise
"Tatinvestgrazhdanproekt".
On the
first site Ilsur Metshin met with the initiative group of shareholders, who are
concerned that construction is not underway for several years. Two houses in
the quarter №68 at the intersection of Amirkhan avenue and Chistopolskaya street
are designed for 320 apartments, all of them are sold. The object, which the
company "Sway" began to build in 2007, had to be commissioned in
2012, but the construction work due to the bankruptcy of the developer were
stopped. As it turned out, the construction was carried out with numerous
violations, because of which houses cannot be put into operation. According to
Azat Nigmatzyanov, it is necessary to strengthen construction of the house -
the facade elements, the internal counter. As the Mayor of Kazan noted, the
elimination of violations will be a top priority to solving the problem of
co-investors.
After an
appeal of Ilsur Metshin to the President of Tatarstan Ministry of Construction,
Architecture and Housing and Communal Services of the Republic of Tatarstan has
instructed to conduct a survey of houses. Experts have made the conclusion that
the constructive part of the building does not meet the safety requirements.
Once the list of the necessary work will be determined,
"Tatinvestgrazhdanproekt" will develop design solutions. "When design
solutions will be ready, we will gather together and outline a "roadmap"
for the terms of entering the houses. Houses were built with violations,
experts of leading Engineering Institute of the Republic say about this. We
then pointed to these violations,"- Ilsur Metshin addressed to the equity
holders.
According
to first deputy general director of State Unitary Enterprise
"Tatinvestgrazhdanproekt" Andrey Morozov, experts will try to prepare
the project documentation as soon as possible - within a month and a half. After
that the estimated cost of all works will be determined, and only then time for
completion of construction can be designated. Interest holders asked the Mayor
if the fact that the investigating authorities evaluate the legality of the
activities of the firm "Sway" and its leader Rashid Aitov is under
arrest will not be the obstacle for the continuation of the construction.
"First there was the question, whether the houses will be completed and
whether residents will receive their apartments. Fortunately our experts gave a
positive answer, it is necessary to eliminate the violations, then we can
finish building of the houses and enter them. The investigating authorities
have not yet completed the check, unregistered assets nominees, including land,
were detected. Real estate investors will be aware of the result of this work, "-
said the Mayor.
With the
second object, which was visited by Ilsur Metshin, exactly the same situation
as with the first develops. Residential multi-storey house on 373 apartments at
st. Dostoevsky, 57 was built with violations that need to be addressed. Today
the house does not meet the safety requirements and cannot be operated.
According to Azat Nigmatzyanov, it is necessary to strengthen the construction
of the building. Following the development of the project activities and the
calculation of the cost, the house will also be included in the "road
map".
The last
point of detour of Mayor of Kazan has become a finished, but not yet handed
over house on 146 apartments, located at the intersection of Bekhterev and
Z.Kosmodemyanskaya streets. Thanks to the work of the city headquarters
facility will be commissioned in the near future, it is expected that the
permission for commissioning will be signed this week. "This is the result
of joint work of staff under the direction of Azat Nigmatzyanov, colleagues
from the Ministry of Construction and contractors. It is a striking example of
the fact that we were able to finish the house, despite the arrest of the head
of the company. I want to thank everyone for their work. For the rest of the
houses it is necessary to wait for design solutions, together with the Ministry
of Construction to develop a "road map" and determine deadlines for
the completion of construction and putting into operation of houses. It is
clear that it is difficult and not enough money, but the investigating
authorities are working to help us – they reveal the assets of the builder",
- the head of the city stressed. Ilsur Metshin assured the shareholders that
every problem house of "Sway" is under control.
Recall, the
company "Sway" is the developer of several dozes of houses,
construction of which started in Kazan in the early 2000s. Problems of the
developer, which subsequently led to the bankruptcy of the company, started in
2008-2009. To date, the LLC "Sway" and LLC "Mag-Story",
which Rashid Aitov controls (since the autumn of 2016 he is under arrest), has 4
houses that remain unfinished in different degree of readiness.