By the first of September, a new kindergarten for 260 children will open
in the yard of the Yaratam residential complex. It is planned to form 14 groups
of 12-20 kids. The construction of the facility started in February 2024, and
today the readiness is 48%. The Mayor of Kazan, Ilsur Metshin, inspected the
construction of the kindergarten on Bukharskaya Street.
For the first time, when creating a kindergarten design project, the design
of the facades of the houses of the residential complex, made in brown and
beige shades, was taken into account. The two-storey facility with a total area
of 2,400 square meters was designed by Tatinvestgrazhdanproekt.
«In spring, we met with the builders and discussed plans for the implementation
of the project. Today we see an almost ready kindergarten. There is no doubt
that the construction will be completed by the beginning of the new school
year. It is very important that the social infrastructure develops along with
the residential complex. The SMU-88 company builds both housing and social
facilities. They have a double responsibility – for the quality of housing and
a beautiful kindergarten for the kids who will live around», – the head of the
city noted.
The residential complex will have four stages of construction for 1,890
apartments with a living area of 9,500 sq.m. Presently, two residential
buildings have been built, the construction of the third is underway, and the
concept of the fourth has been developed. The planned population of the neighborhood,
together with the nearby village of Dalny, will amount to more than three
thousand residents.
«Just recently, it was a depressed area, the former industrial site of
the Kazan construction complex. Today, these are new neighborhoods that are
growing not only with beautiful buildings, but also with social infrastructure»,
–Ilsur Metshin said.
Fourteen playgrounds with shade canopies and two more sports grounds will
be equipped on the territory of the kindergarten. Almost 3,000 square meters of
the territory will be landscaped, asphalt concrete will be laid on 1,400 square
meters, sidewalks will be built on another 1,200 square meters. To date, the
landscaping of the territory has been completed by 10%.
In total, three kindergartens for 600 children are planned to be
completed in the capital of Tatarstan by September. Two preschools – for 260
and 80 places – will be built on Bukharskaya and Yagodinskaya streets, another
one designed for 260 children will be built in the area of Zarechye Avenue in
Salavat Kupere.
«As a result, we will build three new kindergartens for 600 children for
our young residents of Kazan. One of them will be in Salavat Cooper, the second
will be on Yagodinskaya Street and the third will be located here in the
Sovetsky district on Voznesensky Tract Ilsur Metshin», – said.
More than two-hundred people and eight vehicles are involved in the
facility every day. Electricity supply and outdoor water supply were provided
at the facility.
Workers are completing the external sewerage and the installation of
storm drains. Installation of windows (75%) and roofs (30%), arrangement of
entrance groups (38%), laying of floors (30%) continues. Ventilation (50%),
electrics (35%), utilities (31%) and external (41%) networks, as well as
heating (12%) were carried out. In the near future, builders will start
installing heating and low-current networks.