(Kazan City
KZN.RU, April 15, Zilya Ghafi). In Kazan at street Zorge excavation of the left
tunnel from the "Dubravnaya" metro station to "Victory
Avenue" station completed. The ceremony was attended by Tatarstan
President Rustam Minnikhanov, Mayor of Kazan Ilsur Metshin, Minister of
Transport and Road Management of RT Lenar Safin, head of Vakhitovsky and Privolzhsky
districts Andrey Lobov and CEO of JSC "Kazmetrostroy" Marat Rakhimov.
In front of
the assembled Canadian tunnel complex «Lovat» drilled the last centimeters of
soil, guests and 50 subway builders accompanied the end of the work with loud
applause. "Today we witnessed how "Kazmetrostroy" finished the
final tunneling of the first subway line. We have not remained without work in
Kazan, our company has been in existence for 19 years, and Kazan, along with
Moscow and St. Petersburg, is one of the few Russian cities where the subway
construction continues, "- Marat Rakhimov said.
Now at "Dubravnaya"
metro station the main construction works end. "The President instructed
to prepare schedules and cost estimates for the financing to complete the
construction. Now at the station monolithic structure being built, finishing in
the lobbies started (the device of brick walls, buildings and the ventilation
chamber switchboard, smoke removal systems and other works), execution of all
documents for materials for arrangement of the station finishes", - Marat
Rakhimov said.
Today the left
tunnel excavation ended and the right tunnel is ready for laying of the permanent
way. "By the fall we will try to make an examination, and I think, till the
beginning of winter we will get a design decision and will be able to start
tunneling the second metro line. This time will be used for the preparation of
the rings, repair of tunnel boring systems, and we have 4. Scheme of stations is
approved, the landing place agreed with the city. I think that for the City
Day, August 30, 2017, we will put the station into operation fully, that is with
an accomplishment,"- Marat Rakhimov told about the plans.
The next
step will be the construction of the stations of the first stage of the second
metro line. According to Marat Rakhimov, none of metro stations of the second
line will not be put in operation alone. Stations "Fucik", "10th
district", "Lomzynskaya" and "Sakharov" will be commissioned
at the same time, by which time it is planned to build and interchange line. Dates
have not been determined by designers.
Recall the
final construction of the first metro line station "Dubravnaya" and
the design of the first stage of the second line of Kazan underground is underway
since 2014. Excavation of right distillation of tunnel "Dubravnaya" -
"Victory Avenue" was launched March 20, 2015, which was successfully
completed in the summer. December 23, 2015 «Lovat» began tunneling of left
distillation of tunnel length of 672 m.